The weather has finally given us a break and we have been able to
further our progress on the Noll completion. We have completed
laying the flow lines and the electric lines. Both are ready to be
connected. The pits have been filled, a road built and the pads
for the pump jack and the tanks are completed. As soon as the
ground is stable enough to support the equipment, we will install the
work string, move the tanks on location and make final preparations to
place the well in production.
Completion Phase
The operator has reported the 2-06 was perforated and swab tests
conducted. An acid job was conducted to clean the perforations and
additional tests were conducted. The oil is heavy, between 20 and
24 gravity which limits mobility. Additional .75 " perforations
were made to increase wellbore access from the zone.
The utility co-op has been scheduled to bring electrical service to the
lease in January 2007. The operator will continue completion by
setting the work string and surface equipment as soon as possible
thereafter.
|